Most UptoDate Huawei H12-425_V2.0 Exam Dumps PDF 2023 [Q117-Q142]

Share

Most UptoDate Huawei H12-425_V2.0 Exam Dumps PDF 2023

100% Free HCIP-DCF-BFDO H12-425_V2.0 Dumps PDF Demo Cert Guide Cover

NEW QUESTION 117
After the UPS5000-E is installed, what are the key points for the first power-on inspection? (Multiple choice)

  • A. Input and output without short circuit
  • B. Battery wiring is correct
  • C. Whether the mechanical installation and cable installation are tight
  • D. AC input phase sequence is correct

Answer: A,B,C,D

 

NEW QUESTION 118
UPS2000-G (6-20KVA) battery discharge time is significantly lower than the standard time, what may be caused by? (Multiple choice)

  • A. Reduced battery capacity
  • B. Load increase
  • C. The battery is not fully charged
  • D. No mains input

Answer: A,B,C

 

NEW QUESTION 119
What is the possible cause of the high discharge temperature of the NETCOL5000-A air conditioner compressor? (Multiple choice)

  • A. Too little refrigerant charge
  • B. The installation position of the outdoor unit is wrong
  • C. Refrigerant circuit or device blockage
  • D. The condenser is dirty and blocked, resulting in poor heat dissipation

Answer: A,B,C,D

 

NEW QUESTION 120
Regarding the circuit breaker statement, which of the following are correct? (Multiple choice)

  • A. The isolating switch and the circuit breaker play the same role in the system
  • B. The circuit breaker mainly plays the dual role of isolation and protection in the system
  • C. When selecting circuit breakers, do not consider redundancy
  • D. The leakage protection circuit breaker is not recommended to be used in the front end of the UPS system

Answer: A,B,C,D

 

NEW QUESTION 121
When installing NETECL5000-A35KW, generally at least pre-charge () KG refrigerant.

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 122
UPS5000-E has a wide voltage and frequency input range, which can be applied to harsh grid environment and prolong battery life. What is the input voltage range of UPS5000-E with full load?

  • A. 305-485V
  • B. 138-485V
  • C. 105-485V

Answer: A

 

NEW QUESTION 123
Two UPS2000-Gs with different software versions can be connected in parallel.

  • A. False
  • B. True

Answer: A

 

NEW QUESTION 124
At present, in the design of the data center, the part ( ) that most affects the PUE.

  • A. Power supply and distribution system
  • B. Refrigeration system
  • C. Decoration system
  • D. Building Systems

Answer: B

 

NEW QUESTION 125
When Huawei air-cooled air conditioner is installed, the required time for maintaining positive pressure in the refrigerant pipeline is () hours.

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 126
The intelligent busway can replace the precision configuration cabinet and increase the number of cabinets in the IT cabinet.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 127
What are the possible reason of the excessive noise of the NETCOL5000-C fan? (Multiple choice)

  • A. Fan failure
  • B. The filter is dirty and blocked
  • C. The air outlet of the fan is dirty and blocked
  • D. Loose fan installation

Answer: A,B,C,D

 

NEW QUESTION 128
What are the optional functions in PDU8000? (Multiple choice)

  • A. Branch switch hot swap function
  • B. Temperature Monitoring Feature Function
  • C. Input switch remote tripping function
  • D. 9 earthquake resistance

Answer: A,B,C,D

 

NEW QUESTION 129
The location of the data center needs to be evaluated () factors. (Multiple choice)

  • A. Physical and Geographical Conditions
  • B. Building structure
  • C. Cost Factors
  • D. Ancillary facilities

Answer: A,B,C,D

 

NEW QUESTION 130
In video surveillance, if the storage time is short (one week), an SD card can be configured for storage.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 131
When the NetCol8000-C room-level chilled water intelligent temperature control product is booted, which model will it give priority to use? (Multiple choice)

  • A. 130D
  • B. 160D
  • C. 150D
  • D. 190D

Answer: A,D

 

NEW QUESTION 132
NETECOL can assign operation rights to user groups, or directly assign operation rights to users.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 133
FusionModule2000UPS is listed as an integrated UPS and supports up to 125kW.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 134
Which of the following humidification forms has the lowest energy consumption?

  • A. Electrode humidification
  • B. Wet film humidification
  • C. Infrared humidification

Answer: B

 

NEW QUESTION 135
On the panel of the air-conditioning unit, in the group control topology diagram, the difference between this unit and other units is that there is a green frame.

  • A. TRUE
  • B. FALSE

Answer: A

 

NEW QUESTION 136
Which of the following functions or components does the UPS6000-E (50kVA power module) come standard with? (Multiple choice)

  • A. Bus synchronization control function
  • B. Dry contact communication card
  • C. SNMP function
  • D. Parallel function

Answer: A,B,C,D

 

NEW QUESTION 137
When the ECC800 detects that the connection signal to the device is interrupted, it will generate a communication interruption alarm. What are the possible reasons? (Multiple choice)

  • A. Loose cable connection
  • B. Equipment failure
  • C. Poor cable contact
  • D. The power supply is abnormal

Answer: A,B,C,D

 

NEW QUESTION 138
When the UPS is in parallel, the input phase sequence of the main bypass of each UPS needs to be checked, and the output phase sequence of a single pair is not required.

  • A. TRUE
  • B. FALSE

Answer: B

 

NEW QUESTION 139
Compared with the upper air duct air supply, the upper air duct air supply has the advantages of long air supply distance and uniform air supply.

  • A. TRUE
  • B. FALSE

Answer: A

 

NEW QUESTION 140
What is the size of the screen of the air conditioner of FusionModule2000?

  • A. 7 inches
  • B. 5 inches
  • C. 9 inches
  • D. 10 inches

Answer: A

 

NEW QUESTION 141
If the customer has high requirements on the availability of the management system and requires that the normal use of the system is not affected by a single point of failure of the hardware, the NetEco management system can provide a high-availability solution of dual-system backup. In the dual-computer solution, what hardware resources are required by NetEco?

  • A. 2 servers + 1 disk array + 1 switch
  • B. 1 server + 1 t-disk array + 2 switches
  • C. 2 servers + 2 disk arrays + 3 switches
  • D. None of the above is true

Answer: C

 

NEW QUESTION 142
......

Updated Huawei H12-425_V2.0 Dumps – PDF & Online Engine: https://examcollection.realvce.com/H12-425_V2.0-original-questions.html