NEW QUESTION # 44
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?

  • A. To optimize the main import
  • B. To optimize the migration
  • C. To optimize the conversion
  • D. To optimize the activation

Answer: B


NEW QUESTION # 45
You are starting an SAP S/4HANA Conversion. The scenario strategy Downtime Optimized Conversion (DoC) is NOT selectable.What could be the reason?

  • A. The source database is not supported
  • B. The SAP S/4HANA Conversion includes a DMO.
  • C. The SAP S/4HANA Conversion is without DMO.
  • D. The start release is too old for DOC.

Answer: A


NEW QUESTION # 46
You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.

  • A. The transport domain of systems DEV and QAS must differ from the transport domain of system PRD.
  • B. The transport between Unicode and non-Unicode systems is forbidden.
  • C. The upgrade of the PRD must be finished before you import any transports from the upgraded DEV system into the PRD.
  • D. The upgrade of the PRD must be finished before you start new development in the DEV.

Answer: C


NEW QUESTION # 47
You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?
Please choose the correct answer.
Response:

  • A. Perform the Unicode conversion before the upgrade to SAP ECC 6.08.
  • B. Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.
  • C. Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.
  • D. Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU &UC) procedure.

Answer: A


NEW QUESTION # 48
You are performing an SAP S/4HANA conversion for your production system. This conversion requires that certain business functions are switched on.
Following SAP recommendations, how will you achieve this?
There are 2 correct answers to this question.
Response:

  • A. During conversion, SUM delivers some business functions already activated.
  • B. Activate the required business functions manually in the production system.
  • C. Specify the business functions that need to be switched on during the prepare part of SUM.
  • D. Import a transport request from the development system that contains the recording of the activation.

Answer: A,D


NEW QUESTION # 49
You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.

  • A. Migration
  • B. Software update
  • C. Main import
  • D. Conversion

Answer: A,D


NEW QUESTION # 50
What do you need to know about the SAP ERP Upgrade and Update Guide?
There are 2 correct answers to this question.
Response:

  • A. It is a database-specific document
  • B. It contains a section "free space requirements"
  • C. It contains a troubleshooting section
  • D. It is target release specific

Answer: B,D


NEW QUESTION # 51
You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for the last time?

  • A. As part of the cleanup process
  • B. Early in the downtime
  • C. At the end
  • D. Before the downtime starts

Answer: C


NEW QUESTION # 52
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?

  • A. The end of the business downtime
  • B. The start of the business downtime
  • C. The end of the database migration
  • D. The start of the Execution roadmap step

Answer: A


NEW QUESTION # 53
ICNV initialization does 3

  • A. Creation of flag
  • B. Creation of views
  • C. Build index on flag column
  • D. AA

Answer: A,B,C


NEW QUESTION # 54
You are planning an SAP S/4HANA conversion.
Which conversion-specific tasks must be performed during the preparation phase?

  • A. Perform the migration of data to the new data structure.
  • B. Check the compatibility of custom code with SAP S/4HANA.
  • C. Solve problems from the simplification item (SI) checks.
  • D. Run the database migration to the SAP HANA database.

Answer: B


NEW QUESTION # 55
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step
"Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:

  • A. The SAP Support Packages found in the download directory
  • B. The SAP Support Packages that will be bound to the upgrade
  • C. The SAP Support Packages contained in the upgrade media
  • D. The SAP Support packages of the Support Package Stack, calculated by the Maintenance Planner

Answer: A


NEW QUESTION # 56
Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

  • A. Shadow on target creation
  • B. Downtime conversion
  • C. Downtime migration
  • D. Silent data migration (SDM)

Answer: C


NEW QUESTION # 57
You are using the maintenance planner to calculate the required software components for your SAP S4HANA conversion. What do you need to know regarding SUM?

  • A. As soon as the next SP level of SUM is available, the current version of SUM passes into "patch on request mode" immediately.
  • B. AA

Answer: A


NEW QUESTION # 58
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.

  • A. You need to build up an SI check framework by applying SAP Notes
  • B. The errors from the SI checks must be solved, otherwise. SUM will report an error
  • C. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework
  • D. The SI checks are executed in the development system and the results are transported into the subsequent systems

Answer: A,C


NEW QUESTION # 59
You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?
Please choose the correct answer.
Response:

  • A. During the SUM roadmap step "Postprocessing", in parallel with post procedure steps
  • B. After the SUM roadmap step "Postprocessing" and post procedure steps are finished
  • C. During the SUM roadmap step "Postprocessing", after the post procedure steps are complete
  • D. After the SUM roadmap step "Execution" is finished and before "Postprocessing"

Answer: C


NEW QUESTION # 60
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.

  • A. Unicode conversion SAP S/4HANA conversion without database migration Database migration
  • B. Unicode conversion Database migration SAP S/4HANA conversion without database migration
  • C. Unicode conversion Upgrade to SAP ECC with SAP_BASIS 750 including database migrationSAP S/4HANA conversion without database migration
  • D. SAP S/4HANA conversion including database migration and Unicode conversion
  • E. Unicode conversion SAP S/4HANA conversion including database migration

Answer: B,C,E


NEW QUESTION # 61
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:

  • A. By searching for transport requests named <SID>K0<number>
  • B. By searching for transport requests that are assigned to the project SAP_ADJUST
  • C. By searching for transport requests in the file umodauto.Ist
  • D. By searching for transport requests in DIR_TRANS, subdirectory "transport"

Answer: C


NEW QUESTION # 62
You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?
Please choose the correct answer.
Response:

  • A. Credentials of user DDIC in the development client of the development system
  • B. Credentials of user DDIC in client 000 of the shadow system
  • C. Credentials of a named user in client 000 of the shadow system
  • D. Credentials of a named user in the development client of the development system

Answer: C


NEW QUESTION # 63
......

Free SAP E_S4HCON2023 Exam 2024 Practice Materials Collection: https://examcollection.realvce.com/E_S4HCON2023-original-questions.html