If you failed, what should you do?
If you got a bad result in exam, first you can choose to wait the updating of 70-178 exam dumps or free change to other dumps if you have other test. If you want to full refund, please within 7 days after exam transcripts come out, and then scanning the transcripts, add it to the emails as attachments and sent to us. After confirmation, we will refund immediately.
Our website is an influential leader in providing valid online study materials for IT certification exams, especially Microsoft certification. Our Microsoft Project 2010, Managing Projects exam collection enjoys a high reputation by highly relevant content, updated information and, most importantly, 70-178 real questions accompanied with accurate 70-178 exam answers. The study materials of our website contain everything you need to get high score on 70-178 real test. Our aim is always to provide best quality practice exam products with best customer service. This is why more and more customers worldwide choose our website for their Microsoft Project 2010, Managing Projects exam dumps preparation.
How long will you received your dumps after payment
After you make payment, if the payment was successful and you will receive our email immediately, you just need to click the link in the email and download your 70-178 real questions immediately.
What is online test engine?
Online test engine provides users with 70-178 exam simulations experience. It enables interactive learning that makes exam preparation process easier and can support Windows/Mac/Android/iOS operating systems, which means you can practice your 70-178 real questions and test yourself by 70-178 practice exam. There is no limit of location or time to do 70-178 exam simulations. Online test engine perfectly suit to IT workers
About our products
Our website offers latest study material that contains valid 70-178 real questions and detailed 70-178 exam answers, which written and tested by IT experts and certified trainers. The 70-178 exam dumps have exactly 90% similarity to questions in the 70-178 real test. One week preparation prior to attend exam is highly recommended. Free demo of our 70-178 exam collection can be downloaded from exam page.
Microsoft 70-178 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Initiating Projects | - Defining project scope and objectives
|
| Planning Projects | - Resource planning and allocation
|
| Executing Projects | - Project execution tracking in Microsoft Project
|
| Monitoring and Controlling Projects | - Schedule and performance control
|
| Closing Projects | - Project closure activities
|
Microsoft Project 2010, Managing Projects Sample Questions:
1. You need to view Task ID 0 on your project plan. What should you do?
A) On the Format tab, select Project Summary Task.
B) On the Format tab, select Summary Tasks.
C) On the Advanced tab of the Project 2010 options, select Show Status Bar.
D) Insert a new Summary Task.
2. You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A) Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
B) On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
C) On the Display tab of the Project options, clear the Edits to start and finish dates check box.
D) Click New Tasks and change the option to Auto Scheduled.
E) On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
3. You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A) Click the Insert Milestone button.
B) Select the Mark Task as Milestone check box.
C) Change Work to zero hours.
D) Remove the predecessor assignments.
4. You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?
A) Select the Mark task as milestone check box.
B) Set the Constraint date field.
C) Set the Finish date field.
D) Select the Display on Timeline check box.
E) Set the Deadline date field.
5. You are reviewing the task details of your project. You receive the following warning message:
"This task has resources assigned which are over-allocated." You need to be able to identify a possible resolution for the over-allocated resources.
What should you do?
A) Change the task type to Fixed Units, and then recalculate the project.
B) Set the Level Assignments flag to Yes for the task, and then recalculate the schedule.
C) Change the task type to Fixed Work, and then recalculate the project.
D) Increase the task duration values for the task.
E) Use the Task Inspector tool.
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: E | Question # 3 Answer: B | Question # 4 Answer: E | Question # 5 Answer: E |